A can do a piece of work in 40 days; b can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. c alone can do the whole work in?

In this problem, A, B, and C are tasked with completing a piece of work, each with their own timeframes. A starts but leaves after 10 days, and then B continues for 10 days. Finally, C finishes the remaining work in 10 days. Discover how long it takes for C to complete the entire task if working alone

by J Nandhini

Updated Sep 12, 2023

Advertisement
A can do a piece of work in 40 days; b can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. c alone can do the whole work in?

A can do a piece of work in 40 days; b can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. c alone can do the whole work in?

Let's break down the problem step by step:

Article continues below advertisement

A can complete the work in 40 days, so in one day, A can complete 1/40th of the work.
B can complete the work in 30 days, so in one day, B can complete 1/30th of the work.
Now, let's calculate how much work A and B completed when they worked individually for 10 days each.

A completed (1/40) * 10 = 1/4th of the work in 10 days.
B completed (1/30) * 10 = 1/3rd of the work in 10 days.

Now, let's find out how much work is left after A and B worked for 10 days each:

Article continues below advertisement

1 - (1/4 + 1/3) = 1 - (3/12 + 4/12) = 1 - 7/12 = 5/12 of the work is left.

Now, we know that C finished the remaining 5/12 of the work in 10 days.

To find how much work C can complete in one day, we divide 5/12 by 10:

Article continues below advertisement

(5/12) / 10 = 5/120 = 1/24

So, C can complete 1/24th of the work in one day.

To find out how long it would take C to complete the entire work alone, we can take the reciprocal of 1/24, which gives us:

Article continues below advertisement

1 / (1/24) = 24

So, C alone can complete the whole work in 24 days.



Disclaimer: The above information is for general informational purposes only. All information on the Site is provided in good faith, however we make no representation or warranty of any kind, express or implied, regarding the accuracy, adequacy, validity, reliability, availability or completeness of any information on the Site.
Advertisement